[vc_row][vc_column][vc_custom_heading text=”Part of the enabling works for the £350 million brand new Siemens / SSE Keadby 2 power station in North Lincolnshire.” font_container=”tag:h2|font_size:20|text_align:left” css=”.vc_custom_1586351285972{padding-bottom: 20px !important;}”][vc_column_text]Davies Electrical Contacts Ltd were appointed to fit out a storage building and temperature controlled samples storage building. These works were part of the enabling works for the £350 million brand new gas fired Keadby 2 power station.

Contracted services

  • Full Design
  • Lightning Protection
  • Fire Alarm
  • Emergency Lighting & Lighting
  • Chilled refrigeration units with controls
  • Small Power
  • LV Distribution
  • Testing & Commission
  • Contract Length – 8 weeks

https://sse.com/whatwedo/ourprojectsandassets/thermal/keadby2/[/vc_column_text][/vc_column][/vc_row]